Pier Construction Update
All 256 piles for the first phase of the pier construction project have been installed on schedule. Construction of the new main pier extension is also progressing steadily. Crews have installed six precast concrete headers, twelve precast utility trench sections, and thirty precast deck panels, all now grouted in place.